    Las Lomas High School Solar Project

    Solar Panel Location: Front Parking Lot

    Project Timeline:

    Site prep and fences up – June 14

    Construction begins – June 21

    Construction ends – July 18

    Fences down – July 19

    Punch list and testing – July 20 – July 26

    Front Parking Lot Access – None

    Facility Use –Very limited

    Primarily aquatics and school team use

    Parking and drop-off will be in rear of school – from “Whole Foods” entrance

    Other Summer Projects –

    Science classroom in front of school

    LLHS