Miramonte Solar Project Miramonte High School Solar ProjectSolar Panel Location: Rear Parking Lot
Project Timeline:
Site prep and fences up – June 27
Construction begins – July 4
Construction ends – August 9
Fences down – August 10
Punch list and testing – August 11 – August 17
Rear Parking Lot Access – None
Facility Use –Very limited
Primarily aquatics and school team use
Limited drop-off area will be near the pool area. There will be very limited parking.
Other Summer Projects –
Major plumbing infrastructure project will severely limit use of campus and parking availability.
Link to Project Design Plan