Campolindo High School Campolindo High School Solar Project
Solar Panel Location: Rear Parking Lot
Project Timeline:
Site prep and fences up – June 13
Construction begins – June 20
Construction ends – July 22
Fences down – July 25
Punch list and testing – July 26 – August 1
Rear Parking Lot Access – None
Facility Use –Very limited
Primarily aquatics and school team use
Parking and drop-off will be in front of school – near Performing Arts Center